The bridge-torch in Selehard, Russia, 2002


The bridge-“torch” over the river Shaytanka in Selehard. The length of the bridge is 151 m.
The scheme of the bridge is 100+50. On the pylon 3 storeys restaurant is located. The project was developed by Design Bureau of Mostobud in 2000-2001. Construction works were started in 2001, finished in 2002.

The weight of steel: the girder 866 t, pylon 516 t, cables 40 t.
Сoncrete of the piers 3850 m3.